1) Award a base bid only construction contract for the Wood Place, Farroll Avenue/Sandalwood Avenue, Sandalwood Avenue/Cameron Court, & Woodland Drive Back Yards Sewer Lining Project to Nu Line Technologies in the amount of $132,270; 2) Authorize the City Manager to approve change orders for 15% of the contract amount, $19,840, for unanticipated costs/construction contingencies during the construction phase of the project (construction costs = $132,270 + $19,840 = $152,110 + construction management and design and survey costs = $25,332 +$13,968 = $39,300. Total project costs = $191,410).