Committee Member Couch recused himself from the meeting at 2:35 pm.
Planning Manager Perez presented the staff report, including background information about the subdivision, applicable development standards, and the design guidelines for the tract. He explained project details related to the design, colors, materials, and landscaping. He also answered questions about the maintenance of the drainage basin on site.
Mark Vasquez, project designer, spoke in support of the project and explained how the project design responds to the difficult site due to the significant slope and presence of the drainage basin. He also clarified that the roofing material is proposed to be a dimensional shingle.
The Committee appreciated that the structure is well articulated on all four sides and compatible with the site and neighborhood. The Committee found the colors and materials appropriate and was satisfied with the proposed landscaping. It also determined the design to be in compliance with the design guidelines and were supportive of the overall project.