Director Pedrotti provided the following updates to the Commission:
1) There will be General Plan Update Kickoff Meeting in May with the city's consultant
2) The City held community and stakeholder meetings regarding the Halcyon Complete Streets project on April 26th and 27th, 2023.
Commissioner Sackrison asked a question regarding the anticipated timeline of the Halcyon Complete Streets Project. Director Pedrotti stated that it is estimated that the Planning Commission will review the draft plan in June and the City Council in July. Implementation of the project should begin immediately after the design is completed and the estimated timeline for completion of construction is 2025-2026.